Recapping a busy 2017 in Union Terminal’s historic restoration

In 2017, crews worked more than 385,000 hours to restore Union Terminal. As the historic restoration enters its final year, here’s a look at the accomplishments of the past 12 months. Union Terminal’s iconic fountain and plaza, so critical to the historic fabric of the building, was carefully surveyed and

Continue reading

January 2018 construction update

The restoration of Union Terminal is entering its final year and crews are busier than ever. Scaffolding is nearly complete on the west wall of the building where the concourse once extended 400 feet over railroad tracks. This is one of the last major masonry projects to be completed. Art

Continue reading